Greenway Estate, Colebee - Community Corner
Hi radtech , I was also charged the same amount to comply with basix
Greenway Estate, Colebee - Community Corner
Just received an email from champion ! they will not be charging any extras because of the delay !! happy days
Greenway Estate, Colebee - Community Corner
CH people I have spoken with Cora and she said the 3.75% is a straight fee on top of your buildings cost , but she said they are reviewing it…
Greenway Estate, Colebee - Community Corner
@ Greenway15
any chance you could send me a copy of the email too ? I sent her an email trying to clarify what exactly the 3.75 % is but…
Greenway Estate, Colebee - Community Corner
@Greenway15
I have spoken with cora , she said to refer to clause 44.4 in the building contract which says they charge 3.75% of the building contract if building isn't…
Greenway Estate, Colebee - Community Corner
thanks everyone !
So far so good, have had a smooth ride so far with CH they have been quite good with communications so far so fingers crossed it stays that…
Greenway Estate, Colebee - Community Corner
Hi everyone! I'm new on here but have been following this thread for a while so I thought I might as well join up. I Purchased in the 1st release…