Mojo Homes
Yes, I had a bill for extra soil removal. I've had approx 10 variations post contract that were due to the builder.
Mojo Homes
Yes! Me too. Waited 3 weeks for bathroom floor grates which delayed the tiles being layed. Its been another 3 weeks since they started tiling and they still havent finished.…
Inspections
I cant help you with Victoria as I'm in NSW but this was my experience. I also was clueless in regards to building and did not think about inspectors till…
Mojo Homes
I usually get an email every two eweeks and a phone call the week in between. You should definitely contact your SS.
Mojo Homes
I started building 16th Feb and I'm looking at mid Nov completion
A vue of the pines on the Gold Coast
I also like the second one. Good separation of the master and other rooms
Mojo Homes
There was a few weeks delay cause of all the rain recently but I'm upto frames now. Fingers crossed the weather stays nice.
Mojo Homes
I think I went on the construction list around 9/10th Feb. The file went to site 16th Feb and site excavating was done 17th Feb
Mojo Homes
Once I was on the construction list Mojo had started grading the land within 7 working days
Mojo Homes
I'm building the Enigma 36. I can't remember exactly but it was approximately $3500K extra per bathroom for standard tiles
Mojo Homes
I went through council. It only took about 3 days to get the construction certificate. I got email confirmation then the pdf of the signed certificate was sent to me…
Mojo Homes
Yes, that is what the road opening is for. Its to connect your house to the services water, storm etc
Mojo Homes
My builder delt with the construction certificate. From memory once everything was ready it only took 2-3 working days for me
Mojo Homes
I think it depends on your council. I'm Camden council. I just went there, filled in the form and paid the fee. Done in less that 10 mins
Mojo Homes
I do have a tender with another builder from awhile ago, so factoring in recent price rises and the experience of already having been through it with Mojo, I dont…
Mojo Homes
Really worried about quality of the build if they forgot about the foundation of the house
Mojo Homes
Its $6600. But this is probably the 5th or 6th issue I've had with them. The trust level is pretty low. I feel like its a ticking time bomb.
Mojo Homes
Contracts signed last August and council approved last November. I have also already paid 5%. Just told by Mojo that they forgot to charge me for drop edge beams!!! Can…
Mojo Homes
Hi, just finished the pre build stage and about to start construction. Did you get your own building inspector? Would you recommend getting one?
Mojo Homes
Yeps, they can increase the prices as much as they want. I asked my at my last appointment and was told they had 511 jobs on the books at the…
Mojo Homes
I have the July 2016 price list. The Enigma 41 base price is $347,900
Mojo Homes
I would really like to hear from anyone who has started building. How has the building process been?