Beachwood Constructions (Sorrento 27 build) Longwarry
We had handover on tuesday, and i'm pretty happy with what we've recieved - i've updated the album with some quick pics, will take more when the furniture is moved…
Beachwood Constructions (Sorrento 27 build) Longwarry
i've been totally slack with updates lol
Handover is today yay!
Beachwood Constructions (Sorrento 27 build) Longwarry
they're predicting the end of april for completion - we think it will be before then though given how fast things are happening.
Beachwood Constructions (Sorrento 27 build) Longwarry
Been a while since i've update - lots of work has happened yay looking at completion around mid-late april.
i've set this album as public…
Beachwood Constructions (Sorrento 27 build) Longwarry
House is wrapped and ready for bricks when the builders are back from Xmas break
Beachwood Constructions (Sorrento 27 build) Longwarry
We now have framing, they're not wasting any time digging the window frames.
Beachwood Constructions (Sorrento 27 build) Longwarry
And we have a slab
Beachwood Constructions (Sorrento 27 build) Longwarry
Slab was supposed to go down today but due to the weather all we got was a slab frame lol
Beachwood Constructions (Sorrento 27 build) Longwarry
Finally something is happening!
Beachwood Constructions (Sorrento 27 build) Longwarry
We finally have progress, starting the cut and hopefully slab in a week or two
Beachwood Constructions (Sorrento 27 build) Longwarry
We got our planning permit already, it was applied for on 27/9 and approved on 8/10! Just need the building permit which should be another week or so and beachwood…
Beachwood Constructions Melbourne
Anndddddd. We now have settlement Zee Dirt Farm is now mine.
Beachwood Constructions (Sorrento 27 build) Longwarry
LAND HAS SETTLED! woo hoo - the dirt farm is now ours... now to wait for the building permits to be issued.
Beachwood Constructions Melbourne
Finally have a solid settlement date for our land - 26/9/17 - next tuesday yay!
Beachwood Constructions (Sorrento 27 build) Longwarry
So apparently land will title in 2-3 weeks
Beachwood Constructions Melbourne
https://forum.homeone.com.au/viewtopic.php?t=87460
Beachwood Constructions (Sorrento 27 build) Longwarry
So Settlement was supposed to happen today, which it didn't
Apparently instead of titling in June (as we were advised) it will now be happening mid July - the sooner the…
Matt finish to kitchen cabinets - will it look ok?
We've got matt black going on our kitchen cupboards, I think it will look great
Beachwood Constructions (Sorrento 27 build) Longwarry
Colour Selection....
This one was making me paranoid as the only things my husband i can coordinate together are monochromes... so guess what palette we went with? Like
Beachwood Constructions (Sorrento 27 build) Longwarry
So we've now got our build contract and land contract and are signing both tomorrow - there was a bit of a kerfuffle with the developer as they did not…
Beachwood Constructions Melbourne
We are also starting the process to build with Beachwood Constructions - i've started a thread where i'll update on our experience and progress with them.
Beachwood Constructions (Sorrento 27 build) Longwarry
Exciting times ahead - we got pre-approval from our bank (Westpac) a few weeks ago and decided to start looking for a builder to do a H&L package in Pakenham/Cranbourne.…