Variations invoice 8 months after completion
Thanks.
there is literally nothing written in the contract in regards to any variations. the only prices we ever got told about are the prime cost items such as carpet, tiles…
Variations invoice 8 months after completion
Thanks!
Yeh hubby went over the contact last night and there is nothing about 2% in our contract either.
It's something the builder mentioned when we raised concerns about the initial invoice.…
Variations invoice 8 months after completion
Oh okay.i don't really get it...I'll pass it on to my husband! Cheers!
Variations invoice 8 months after completion
What do you think about the 2% part here?
Variations invoice 8 months after completion
No waa always just orally! if things had of been on paper with the price then we would have had the ability to say no. As we knew we had…
Variations invoice 8 months after completion
I am away from home so can't check my copy of the master builders contract but most contracts i have seen require a consent from you before variation work is…
Variations invoice 8 months after completion
Our house was completed in December 2016.
It is now 8 months later and we have received a variations invoice that is much more than we anticipated. Being so late, we…