
Metricon Sentosa 52 Modified
do you have a photo pf the drain in the bath, just want to check they have installed the right one in my house?
it is meant to be chrome

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Facade coming together

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
some scaffolding down

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Front facade coming along nicely

Metricon Sentosa 52 Modified
You should have a cabinetry drawing if you met with joinery which has the drawings you would have signed off on

Building with Metricon
i paid per bedroom
not sure yet as still currently being built not up to plastering yet

Metricon Sentosa 52 Modified
Should the bottom of the door frame be metal or wood the rest of the door frame is wood with the base plate aluminium

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
roof tiles just about done

Metricon Sentosa 52 Modified
I much prefer everything being fixed before moving in than having to chase them up after.

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
top started today

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
No only bottom

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Slab pour a few weeks ago

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Slab pour tomorrow

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Drove past today and power is in so should have slab in by late next week

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Screw piles have gone in

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Just hit the first snag, during boring of second half of piers the boring failed due to cave in. Now has to go back to engineers

Metricon Sentosa 52 Modified
Do you have your kitchen cabinet drawings? How is it there? Is it squared and to the ground? If not the same they need to pul it out and redo…

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
And Sorrento doors

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
I did upgrade all doors in the the house to Hume lin1

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Site cut started today. Was told start date was tomorrow. Only found out as neighbour called me

Building with Metricon
I was also wondering about the need for a second hot water unit - was thinking pressure was more of a concern than hot water supply as adding a second…

Building a Metricon Hampshire 45 KDR in Melbourne Provincial
Site start date this Friday - cant see them doing more than a site cut maybe