The CARLISLE HOMES & SPECTRA General Information Thread
Our building experience has not been the greatest but not the worst. We built double storey homes and finished in five months.
Start from the sales through colour selection and tender…
RE: Harcrest by Mirvac
Hi Anj85,
We have the asset protection permit done not too long after the land settled, am not sure who organised it, but one day I got a letter from the…
RE: Harcrest by Mirvac
Hi anj85,
We got our design approved by Mirvac about three weeks ago and just got the building permit last week.
Our builder advised that they will commence the site cut this…
The CARLISLE HOMES & SPECTRA General Information Thread
Hi Guys,
How often do you guys visit your site? Once a week? Everyday?
The CARLISLE HOMES & SPECTRA General Information Thread
Hi All,
Just wondering to anyone out there who had passed the first hurdle with the building foundation.
I received the soil test report from CH this morning and our land is…
RE: Harcrest by Mirvac
Hi anj85,
What a coincides between your post today and an email that I received from Mirvac's CRS.
I received an email this evening from Mirvac advising that:
"In December we wrote to…
RE: Harcrest by Mirvac
Hi Neel,
Much appreciated for your response. I am sure I will PM you in the near future to get some assistance.
Have a safe Christmas & Happy New Year.
RE: Harcrest by Mirvac
Hi nnsha1,
How's your overall dealing experience with Mirvac post settlement and after you finished building?
Did they approve your house design, garden landscape, mailbox, driveway, etc without too much fuss?…
RE: Harcrest by Mirvac
Not sure if everyone already received the letter from Mirvac.
They are saying that the progress of the civil works are ahead of schedule, we may even see the settlement…
RE: Harcrest by Mirvac
Hi anj85,
I have the same issue with this delayed, I have to re-arrange the children's school arrangement because of this delay plus few other things that we had planned.
I don't…
RE: Harcrest by Mirvac
Hi All,
I am also in stage 8. I was also under the impression that there are stage 6 & 7 in front of us, but it turns out that they…
The CARLISLE HOMES & SPECTRA General Information Thread
Nick2k,
That data point cost is definitely too good to be true. I paid $154 per point and ended up only have 4 for the whole house. I will figure out…
RE: Harcrest by Mirvac
Thanks Kiwiland for your response.
It's certainly makes sense that the council will be the one that dealing with all of the stuff post hand over when the Mirvac finished the…
RE: Harcrest by Mirvac
Hi Kiwiland,
Sorry to hear about the delayed on your land settlement.
I am in stage 8 and did receive the same letter regarding the storm water which to me is…
RE: Harcrest by Mirvac
It is just baffle my head that the delayed is happening on every stage release.
Surely, after releasing few stages in the past Mirvac would have learnt the lesson in getting…
RE: Harcrest by Mirvac
Hi nnsha1,
Thanks for the kind words and hope to see around too in the estate.
That's disappointing for having to postpone a little further. It's just kills the excitement, doesn't it?…
RE: Harcrest by Mirvac
Hi nnsha1,
It sounds very exciting to finally have the land settle after the delayed.
I bought the stage 8 and was told the settlement will be in July -August this year.
Which…
The CARLISLE HOMES & SPECTRA General Information Thread
Wondering if anyone out there upgrade the kitchen bench and the breakfast island to 40mm thickness? Do you know the price to upgrade from 20mm to 40mm?
Thanks