House and Land Package advice
Hey. The exact line written into the "Project Building Specification" was "Fixed site cost included", and another line saying "Including rock removal".
From what you're saying, is this sufficient? I…
House and Land Package advice
Bump/update.
Met with the agent today. The HIA contract was not amended, but the building spec contract was. Is this sufficient? Or do I need the clause to be…
House and Land Package advice
Thanks for the advice guys.
This is my situation at the moment. The contract has clauses which state I have to pay for removal of rocks, extended drainage, etc. …
House and Land Package advice
Just bumping this thread.
In summary, what I wanted to know is: How much more can I expect to pay "if" I can't renegotiate to a fixed priced contract?
Obviously, if I…
House and Land Package advice
No, but the description of the package did state "included site costs".
Are site costs the main thing I need to worry about?
Please tell me what could blow out, and by…
House and Land Package advice
Thanks for the reply.
I have something in the contract which states there is an allowance of a $2000 for site costs.
It doesn't go into details, but I was told this…
House and Land Package advice
I've noticed a few views, but no replies.
If any extra information is required to clarify, please let me know.
I'm eager to sort this out soon, as the contract needs to…
House and Land Package advice
Hi everyone,
I've just stumbled onto these forums after some googling, and would like to request some advice please.
I've recently gotten into a house and land package. I've paid $3000…