Building a new Mainvue Emporio 430
I think he meant the house will be ready to move in three months... he probably forgot to factor in the time it will take to rectify the issues Darbecca…
Building Mainvue Emporio ER430 Ultima
Hi Vino,
Good to see the progress on your build.
Our construction has started, pre-pour done, but the pouring of the slab has been pushed out to next week because of the…
Building a new Mainvue Emporio 430
The construction has begun!
Site Cut - Done!
Drainage Pipes - Laid!
Slab pour - 09/03
The construction supervisor is confident the house will be up in three months...
It worries me…
Building a new Mainvue Emporio 430
We've got a perfect Christmas gift this year - our land settled yesterday - Christmas eve...!!! yay!!!
We're hopeful that the build will commence in February - at least that's what…
Mainvue Emporio ER430 - Knockdown and Rebuild
Thank you Michael and Sassid, this surely helps.
I did suspect the overhead cabinets will hinder the installation. Its strange our admin hasn't brought that up yet Like
Mainvue Emporio ER430 - Knockdown and Rebuild
Hi Michael, I've been following the progress of your home, and I must say it looks great
We're also building the Emporio 430 in the South…
Building the Emporio ER432 with MainVue / Henley
Hello sassid, Congratulations
I am new to the forum, we're also building an Emporio 430 and signed our tender and contract today.
I've been silently following…
Building a new Mainvue Emporio 430
Good evening everyone! My first post here.
We're building a new Emporio 430.
Signed the tender and contract today, yay!