Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Handover was a few weeks ago. Will put pics up soon

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Swapping living and alfresco is a standard option, so we did that to fit a pool in between the alfresco and our left boundary fence, plus the balcony on the…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
When i was going through tender stage, there were 2 things plantation wouldn't move, the kitchen and the stair case. I did originally try to move the kitchen across…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
One thing that was annoying was the location of the bath tap in the master ensuite. By default plantation placed it on the wall on the far side of…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
That's exciting. What stage are you at? We've learnt alot through the process so far and are about 1 month away from handover. There's a few things…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Cladding done, top exterior painted and staircase

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
More pics showing plaster boarding and colour selections...

Any tips on how to design your electrical plan?
From my recent personal experience, my advice would be:
* Make sure you think about cat6 data cabling. I have at least 1 ethernet port going to all bedrooms and…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Latest pics. Roof, Windows, Aircon, brick and render.

Plantation Homes Question Re: Cesarstone.. Anyone know?
That's interesting because i also wanted a Rinnai and was told i couldn't have it. Must depend on who you talk to unless they've changed their policy or…

Plantation Homes Question Re: Cesarstone.. Anyone know?
Hi,
I'm also building with plantation and am in production stage. We also went through the same thing as you, trying to use different suppliers for some things. In…

Building Plantation Trinity Lux Q1 @ Oxley - Brisbane
It looks bigger than 600m2 in the pics. The wider street frontage makes a difference. Mine is also 600m2 but 15m street frontage which goes down to 14m because of…

Building Plantation Trinity Lux Q1 @ Oxley - Brisbane
We're at the same point with our plantation build just down the road in Sherwood. Ill be following your progress. Looks good so far! Nice big level block you've got…

Plantation Mirage Vogue Q2 Build - Mango Hill, QLD
I've just started my topic on my mirage vogue Q1 build in sherwood...
viewtopic.php?f=31&t=90591

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
House Frame
The house frame has gone up incredibly fast...3 days so far. Unfortunately not fast enough to get the roof on before the christmas break, so it's all left open…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Slab
After more delays due to rain, the slab was done on the 8th and 9th of December. Our site supervisor was hopeful of having the frame and roof done before…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Plumbing
After the pool shell was done, it was time for the plumbers to dig trenches and lay pvc pipes before the slab was poured.

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Pool Shell
After weeks of delays because of rain, we got our pool shell dug out and concreted. It rained heavily after we dug the hole, but fortunately the walls didn't…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Build Starts
The build started and the first thing that need to be done was the site cut and fill, followed by pouring the concrete piers. The piers went to…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Existing House Removal
There was an existing house on the block that we needed to get demolished. After getting a few quotes for demolition, coming in around the 13K - 15K…

Plantation Mirage Vogue Q1 Build - Sherwood, QLD
Hi All,
I thought I'd start a topic for my build of the Plantation Mirage Vogue 43 (previously called the Q1), on a 605m2 block in Sherwood.
The floor plan is below.…

Plantation Mirage Vogue Q2 Build - Mango Hill, QLD
Hi CharlieVH,
I was wondering if you had any more updates on your build?
We've just entered construction stage, and the site cut and fill happens on the 18th of October.

Plantation Mirage Vogue Q2 Build - Mango Hill, QLD
Hi CharlieVH, I'm also building a plantation mirage vogue Q1 in Sherwood. I'll also create a forum for my build, which hasn't started yet. I need to get…

Framing Stage
Hi,
No we're not at Arbour Reach. It's a demolish and rebuild on Borden St.

Framing Stage
Hi,
I'm thinking of building the mirage Q1 in Sherwood too. How has your experience with Plantation been up to this point? Just wondering about the build quality and…