Builder threatened to terminate our contract!!!
I don't think I should name them on this thread, given my level of dissatisfaction.
But research your building company thoroughly before you sign a contract, I saw some…
Builder threatened to terminate our contract!!!
Well, the jaw dropping surprises keep rolling our way with this builder...
The builders pegged out the property end of February 2013!
Mid April - 7 weeks later to lay the pad!!
Start…
Waterhall Estate - here we come cause we have bricklayers!!
http://s1287.photobucket.com/user/jayney35/library/?sort=2&page=1
Ha!Ha! Nope it didn't. Will try again tomorrow,
Waterhall Estate - here we come cause we have bricklayers!!
Everyone, welcome to my little house... Pictures so far
Hope it works!!
Waterhall Estate - here we come cause we have bricklayers!!
Thanks imille, I will try your suggestions. Are you building in WA?
Rex's Redink build - LANDSCAPING
It looks like really big house Rex! Bricks are similar to ours, what colour roof are you going?
Waterhall Estate - here we come cause we have bricklayers!!
Thanks Rex,
I think there is about 5 of them. We don't have a lot of brickwork, because we have so many windows. I shouldn't think it…
Waterhall Estate - here we come cause we have bricklayers!!
That's right, 12 weeks after the slab being poured we had a team of bricklayers start yesterday!!
11 weeks since pad done - still no bricklayer !!!
Yes, Hamilton our SS did warn us about the shortage but 11 weeks is far beyond what anyone else I have known for delays. We have been given a…
11 weeks since pad done - still no bricklayer !!!
We building in South Guildford, Waterhall estate
11 weeks since pad done - still no bricklayer !!!
Any bricklayers out there who can help us out? Our builders say they can't find anyone? I'm desperate.
Rex's Redink build - LANDSCAPING
They're motoring along, and it looks like a nice neat and tidy job too. APPARENTLY it all just flies along from here - lol how many times have we…
Waiting six weeks for slab pour, seven weeks for bricklayer?
Thanks Tracyw, I was still optimistic at 6 weeks. But hearing that they turned away single operator brickies made me pretty annoyed.
Waiting six weeks for slab pour, seven weeks for bricklayer?
Unfortunately, we had already signed the contract with that builder before those reviews happened, I have chatted about the bad reviews with my supervisor and begged him not to put…
Rex's Redink build - LANDSCAPING
At least it progressing. The crazy thing is the builder advertised for builders but turned away single operators, only wanted teams. I was like "are you crazy,…
Rex's Redink build - LANDSCAPING
Oh my God Rex777, your house brickwork is halfway there?? We are still waiting for our builder benchmark designer homes to confirm a bricklayer, it has…
Waiting six weeks for slab pour, seven weeks for bricklayer?
I know, I consider myself fairly understanding but this is just taking too long! Next door was only waiting 3 weeks which is what the pad need to cure…
Rex's Redink build - LANDSCAPING
Hi rex777, I hope you have your bricklayers soon, we have been waiting 7 weeks for ours and we got told yesterday, they have been delayed at previous job so…
Waiting six weeks for slab pour, seven weeks for bricklayer?
Thanks 1rocky and cinder!
Cinder- they are nota big builder, refer to themselves as boutique sort, on their website they say they take on about 60 builds a year…
Waiting six weeks for slab pour, seven weeks for bricklayer?
What I am trying to find out is if anyone else has had these kinds of delays with brick layers, because I have been very attentive with the builders but…
Waiting six weeks for slab pour, seven weeks for bricklayer?
Thanks 1rocky but we don't get to speak to out SS, we have to go through a girl in the office called a Client Liaison. I email her, she…
Waiting six weeks for slab pour, seven weeks for bricklayer?
Hi everyone
So in mid February we had our pool shell completed in which it took six weeks to get the slab poured?…