Building with Metricon
We were told by M that they don’t require OC for handover. Some banks do require this before releasing the final payment. However, for us CBA advised this isn’t a…
Building Metricon Liberty 40 Schofields
Thanks mate,
Yes, great suggestion & yes it will be harder to clean when we have a total of 6 showers!.
All the best with your build
Building Metricon Liberty 40 Schofields
Thanks mate,
We wanted an extra master bedroom. That's something we always had in mind so that was the first requirement we told every consultant we met as no standard design…
Building Metricon Liberty 40 Schofields
Thanks Judder,
It works out to 45 squares now.
We only reversed the front coz we had to as per the land requirements. But pretty happy with how it worked out in…
Western sydney property group/ town house & villa
Is this on 100 boundary road Schofields?
Building Metricon Liberty 40 Schofields
Delayed post. Heaps of progress since last update.
Exterior:
Frame completed
Hebel completed
Rendering almost complete
Interior:
Gyp-rock done
Bathrooms water proofing done
Electrical & aircon roughings done
Kitchen cabinets & stair case done
Building with Metricon
Thanks Shokel,
Would you still recommend it if not in bushfire prone area?
Building with Metricon
Hi guys,
I just wanted to check if roof sarking is a standard inclusion for Metricon homes? As we were not asked about this during the consultation stage & the guys…
Building Metricon Liberty 40 Schofields
So good to see the frame almost completed. Had a chat with the building inspector yesterday who advised the following will be done in coming week:
1. Building scaffolding
2. Top…
Building Metricon Liberty 40 Schofields
Hi bud,
Build is going fine. We just received the 2nd invoice for the frame stage.
We did engage houspect for 5 stages. They did point out a couple of critical errors…
Building Metricon Liberty 40 Schofields
Thanks Simon,
We actually ended up getting a lot of upgrades & we only had the $15K package
The must have upgrades could be upgraded carpet, size…
Building Metricon Liberty 40 Schofields
Yes.. all doors & windows are increased to match the ceiling height
Building Metricon Liberty 40 Schofields
Had a chat with the site manager this Monday who advise that M somehow forgot to order the steel frames when they ordered the material for the framing. It’s been…
Building Metricon Liberty 40 Schofields
Thank you.. we have a step down in our slab so the front of the house & garage have 3.2 mtr ceiling & the rest of the house has 2.7
Building Metricon Liberty 40 Schofields
Thanks Ned.. hope you’re built is going well too
Building Metricon Liberty 40 Schofields
Guys had been busy whole of this week to put the frame.. hopefully first floor to start soon & then the rooofing
Building with Metricon
Try to get in touch with your construction manager?
Building Metricon Liberty 40 Schofields
Yep, 3.2 mtrs.. hope it looks good thought! We never knew when we purchased the land
Building Metricon Liberty 40 Schofields
I would say anything as part of the slab would definitely be more solid & long lasting than a seperate concrete pour that is more prone to cracks etc.. but…
Building Metricon Liberty 40 Schofields
Hi Wild,
The garage & portico were included in the slab pour. When we had the initial plans they didn’t include the portico & told us it isn’t standard. However, M…
Metricon - Chelsea 37
Sorry to hear mate.. did you get an external inspector to review the slab by any chance? Can’t believe M couldn’t get the slab right
Building Metricon Liberty 40 Schofields
Haha yeah.. love big shower area . Though my wife was in favour of getting at least 1 bathtub but in the end we decided to…
Building Metricon Liberty 40 Schofields
Slab has been poured today!! Should be able to post few pics on the weekend 😊