Building with Bentley homes
Feel sorry for that thing happened to you.
May i know which area are you in?
My house is at lock up stage as well, and of course…
Building with Bentley homes
How is everyone 's house going?
They have finished my frame stage.
And bad news is
They still havent get the power connected wirh Red Energy. I have tried to talk red energy…
Building with Bentley homes
@crh66: hopefully there is no problem with mine
@barry: i have already contacted an inspector,hopefully he can point out some issues before the plaster.
How is everyone's house going?
Building with Bentley homes
After discussing with the manager of bently homes about this matter! i have told him that my neighbour has allow me to use their power until the site got connected…
Building with Bentley homes
Hi guys,
Has anyone got charged by Bently homes for the generator's cost?
Currently i have been noticed by Bently homes that the electricity is not available at our site due to…
Building with Bentley homes
Yes,finally.
They emailed me on 18/11 saying that works has been commenced on 14/11.
And
Our slab has been poured 5/12 which is 1 day earlier than intended.
I will come out to take…
Building with Bentley homes
We have land titled for close to a month already. Still havent got a commence date for building. How long did you have to wait for starting up?
@lilyh2o:
I did try…
Building with Bentley homes
Hi guys,
I am also building with Bentley Homes(Radisson 250 with Glen Facade), They have been very helpful so far. We will start our Base stage in next couple of weeks.
Is…