4PostsMost Active Topics
2 years2 yearsKrisb123 posted:
Build not to plans - advice needed
Build not to plans - advice needed
Hi, glad it could be sorted. We ended up terminating the contract and the Qbcc also found in our favour. But then the builder asked fir an internal review…
3 years3 yearsKrisb123 posted:
Build not to plans - advice needed
Build not to plans - advice needed
Are you in QLD? Because yes we are at n the same boat. Roof not built to plan and soooo many defects. You can get the certifier out whenever you…
3 years3 yearsKrisb123 posted:
external doors and waterproofing
external doors and waterproofing
We are doing an extension on our house and it is going very badly indeed.
Actually going through a EDR with the QBCC (QLD) due to the many many…
3 years3 yearsKrisb123 posted:
Contract: Charge on the land and change of stage definitions
Contract: Charge on the land and change of stage definitions
I had the same - builder wanted a bigger slice by lock up. It’s been a disaster as the wok was very bad. But if you terminate the contract, they…