Footing Variation with controlled fill
Thank you Matt
I am waiting for the builder's reponse so far. And , I will make a decision soon. Thank you for helping me analyse this footing variation issue.
Nice weekend:)
Footing Variation with controlled fill
Yes, oneJohn. I think you are right.
How is your building status now?
Footing Variation with controlled fill
Hi oneJohn,
I saw Waffle slab on my initial contract. I thought it is still the same. Maybe because the engineering has redesigned my footing
into reft slab.
Just comparing the soil…
Footing Variation with controlled fill
Hi Insider
Thank you for the post.
Yes, it is P(past Tree Removal).
Yes, the report design with the piers.
Footing Variation with controlled fill
Got the phone call from the developer, was told the land next to my neighboure which is building with our company too. their footing report a little better than me.…
Footing Variation with controlled fill
Hello oneJohn,
Thank you for the post.$20k is only for the extra sitework & footing above the standard.Combinging other site cost all up is 25k for a 164m2 house.
I will check…
Footing Variation with controlled fill
Hello Matt
Thank you for your post. Yes, it is waffle slab with brick veneer .
My footing schedule:
Type Beam Size(mm)WidthXDepth Reinforcement top …
Footing Variation with controlled fill
The rrason why I trusted them. As my bf's building on the same street and get heaps footing heaps drop after supplied the certificate of controllef fill.So,I felt confident to…
Footing Variation with controlled fill
Thank you for the post.I am in Adelaide. Unfortunately, I have signed the contract. Yes,builder will not do anything. I think like you said I will do independent soil…
Footing Variation with controlled fill
Thank you guys for the reply. Sorry for the wrong information on my post. The several houses away from mine isP/H1-D.I put the wrong code last Night. Just wondering how…
Footing Variation with controlled fill
Yes, I did give the controlled fill certificate at the start as I worry my footing variation will be too much.
Footing Variation with controlled fill
Yes, these two blocks are built under same group but with different engineering companies. I am thinking whether worth to do another soil test by the independent engineering company .
Footing Variation with controlled fill
Hi Bashworth
Thank you for your professional replay. I have recently read some your posts which I have learned some knowledge for building.
This new estate was the reserve, with some tree…
Footing Variation with controlled fill
Hello Everyone,
I am new to here. Try to enjoy the building procedure. But now I am having a little trouble after the soil test.
My land is on the new…