Palace 41 Dream Home
1st Floor Completion
Stairway Space, Butlers Pantry Kitchen
Steel Beams in for Garage, Main Exit to Alfresco and Kitchen/Grand Dining
24th March 2019
26th March 2019
Palace 41 Dream Home
Partial Frame Erected
Study, Theater Room, Laundry and Grand Dining boxed.
It all seems to be moving along well.
Weather is ideal for builders.
19th March 2019
* Image from rear showing Grand Dining to…
Palace 41 Dream Home
Timber starts arriving on site
17th March 2019
Layout of Ground Floor Wall Positions Starts
18th March 2019
Palace 41 Dream Home
Slab Pour
5th March 2019 - All day activity
12 cement trucks required
Timing OK, the trucks appearing before the one present had finished unloading
Only a couple outside the recommended 20min spacing.
All in…
Palace 41 Dream Home
Had some delays due to some very hot days that made both working and slab pour unable to be done.
Works scheduled to prep for slab pouring not initiated until 03/03/19.
Boxing…
Palace 41 Dream Home
So we moved out of our home July 2018 in preparation for its demolition.
We thought we would be generous and donated a lot of the internal fixtures (doors/cabinets/fittings) and the…
Palace 41 Dream Home
Piping in.
25th February 2019
Looking forward to counting the cement trucks as they roll up on the 28th February.
Palace 41 Dream Home
The dunny is on site.
All systems go, Henley finally step on site.
6th February 2019
Palace 41 Dream Home
Colour Appointment - Cabinets & Fittings
One thing i must mention here is ensure that bulkheads are fitted to all overhead cupboards (unless you want to store stuff up there where…
Building Palace 33 with Henley in West Mel
I am currently building Palace 33 with Henley, and now it is in construction stage.
I have got great help in the forum by viewing people's experience, and inspired…