liquidated damages Xmas holidays
liquidated damages Xmas holidays
Tx Bashworth, Bluesuede and Forg. There is nothing in our contract specifically about Xmas.
10 years10 yearsmorgan76 posted:
liquidated damages Xmas holidays
liquidated damages Xmas holidays
Our builder has exceeded the contract build time by 24 days, but only wants to pay out 3 days worth of liquidated damages because of the 21 day Xmas break.…
10 years10 yearsmorgan76 posted:
Help! Builders Notice of Delay Post Contract Finishing
Help! Builders Notice of Delay Post Contract Finishing
I think "complete" is practical completion.