Hi all, I've lurked long enough now I'd feel bad if I didn't put up a thread for our build so here goes.
Bit of background, the wife & I had…
PLEASE USE AN INDEPENDENT BUILDING INSPECTOR!
I'm building with Simonds, and while I had minor issues with my site supervisor and his boss early, the structural part of the build was fine.
As I do with…
KDR - Rawson Balmoral (Modified) Sydney NSW
How many rain days have been claimed so far?
Rawsons contract states that notice for extension of time claims are to be given "at the completion of the building work", so…
KDR - Rawson Balmoral (Modified) Sydney NSW
Don't let anything I've written put you off Rawson. I actually rate them fairly highly... for a volume builder. I just write about our experience to help others know what…
KDR - Rawson Balmoral (Modified) Sydney NSW
^^ this!!
After the first month of the sales process we sensed what a flustercluck the preconstruction administration was and consciously made the decision to document everything in writing from that…
KDR - Rawson Balmoral (Modified) Sydney NSW
In addition to hiring a building consultant to make progress stage inspections, download and read the NSW Department of Fair Trading Guide to Standards and Tolerances, buy some measuring tools…