2 years2 yearsrobw17 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW
KDR - Rawson Balmoral (Modified) Sydney NSW
Week 5 Construction
The slab was left to cure so it was a very quiet week. Quite boring actually... a bit like, well, err, watching concrete cure. The only things that…
2 years2 yearsrobw17 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW
KDR - Rawson Balmoral (Modified) Sydney NSW
Demolition
The original house was of double brick & tile construction with two bedrooms and the original kitchen and bathroom. We purchased the property with the intention to knockdown and rebuild.…
2 years2 yearsrobw17 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW
KDR - Rawson Balmoral (Modified) Sydney NSW
We're doing a knockdown/rebuild with Rawson Homes. We've completed the preconstruction administration and our file was handed over to construction on the 1st July. The design is based on the…
3 years3 yearsstaceytryon posted:
KDR - Rawson Balmoral (Modified) Sydney NSW
KDR - Rawson Balmoral (Modified) Sydney NSW
Looking very good. We too are in the Southern Suburbs about to have tender meeting so a little nervous about the whole process, but your stages of updates and…