2 d2 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Hi Ranti, it depends builder to builder. In general practicee Tender comes 1st and then contract. Who is your builder and are you signing home plus land ?

  ⋅  1
5 d5 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 16 Update - Last week was full of action packed. The wet areas have now been sealed, lower eaves completed, Electrical rough in completed, Balcony Decking & Cedar batten…

9 d9 dvin83vin83 posted:
Issues Building with rawson homes

Hi Ali, at the moment I am underway of my house construction with Rawson. So far my experience is good with them. Right from pre construction till date, they have…

13 d13 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Thank you Sunny. I am following you build story on instagram.. You are not far to see the roof trusses on and tiling done on other day. Have you got…

14 d14 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 15 Update - This week we see good progress. The lower roof tiles are now completed, Lower Fascia and Gutter have also been completed for Ground, Metal roof over…

  ⋅  1
21 d21 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 14 Update - The eaves and cladding work have now been completed and the painter has finished on the external. The scaffold has now been lowered and reset for…

27 d27 dvin83vin83 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW

Hi Rob, progress seems good. Who did identify the issue with wrong bolting ?.. Was it the independent inspection or the Site Supervisor itself ?

29 d29 dvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 13 Update - Roof tiles have now been completed. The eaves and cladding materials have been installed. Downpipes have also been installed. Seems like majority of External work have…

1 month1 monthvin83vin83 posted:
Rawson Seaview 36 - Schofields

Thanks Rob. Things are moving really fast at sites, I might be very optimistic but if things go same manner I believe PCI may come my mid December.
I gone…

1 month1 monthvin83vin83 posted:
Rawson Seaview 36 - Schofields

Sorry guys for the alignment of the photos, somehow unable to have them attached as they should be.

1 month1 monthvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 12 Update - With the clear weather in past 2 weeks work seems to be running of very fast pace. At end of week 12, Brick work completed Roof…

1 month1 monthvin83vin83 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW

Hi Rob, the timber roof trusses have been installed and the brickwork has been completed. I am expecting this week Fascia gutter installation should be completed and aiming to complete…

  ⋅  1
2 months2 monthsvin83vin83 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW

Looks Good Rob. Have you got your Frames ordered ? Hopefully if the weather remains good, next 4-6 weeks you will be able to see the external structure of the…

2 months2 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 6-8 Update - Bricklayer has attended the site and commenced the bricks on ground floor. Week 7 was all rainining so nothing much happened. Got an further email from…

2 months2 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Yes Rob, what I experienced that once they on site, things move fairly quick. Only problem is lead time during the 1st payment milestone and ordering of frames and stuff.
I…

3 months3 monthsvin83vin83 posted:
Issues Building with rawson homes

Thats tough to hear Jo, so hows the situation now ? Has Fair Trading assisted you in regards to reach to any conclusion with Rawson Homes ?

3 months3 monthsvin83vin83 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW

Hey Foxpro, 5-6 months is the basic (including council approvals) what it takes to reach on the construction stage. I tried to keep the process very fast and still it…

3 months3 monthsvin83vin83 posted:
KDR - Rawson Balmoral (Modified) Sydney NSW

Good luck Rob, the design looks really great. Specially I loved the Workshop you have planned for.
Where are you building in Sydney ? Have you got any Estimation to complete…

3 months3 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 5 update - the frames have erected and windows installed. Quite happy as in past two weeks things were dead slow and suddenly the structure is here.
Have received…

3 months3 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Week 4 Update - not much happened in past two weeks. Got thr slab work done in 1st week of June and since then plumbing and termite treatment happened.
Got email…

3 months3 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Hey Mate, what I understood from the SS that Tyyrell is what they use as per their internal processes. Tyrell report is to be used as baseline and signing off…

3 months3 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Hi guys can you suggest who shall I engage for prelining inspection. Rawson confirmed that they will be using Tyrrell for the same however I still want to bring my…

4 months4 monthsvin83vin83 posted:
Rawson Home Review

Great news Parele. Be ready for your 1st invoice probably in 2-3 days. My slab pour finished last week only so I am almost on the same stage as you.
What…

4 months4 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Thats great mate. They are indeed highly organised and follow the process they have defined. All the best for upcoming appointments. By the way where are you building.

4 months4 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Sounds good mate. So whats next, you signed up for the tender and progressing for the internal and electrical appointments. try to be fast on discussions and approvals, as I…

4 months4 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Hows your plan presentation gone mate. or is this is scheduled for 15th June ?

4 months4 monthsvin83vin83 posted:
Building a Rawson home at Wyee, Central Coast.

Hi Amy, your house looking really good. I am keen to see once they start working on the internals and how that coming along.
Slab pour at my side also…

4 months4 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

Yes Norfolk. I am planning to have independent auditor at Pre-lining stage and prior to handover. Do you think, should I change it to some other stage.

4 months4 monthsvin83vin83 posted:
Rawson Seaview 36 - Schofields

He have also confirmed me that dimensions are right as per the plan and if any changes happen he will submit a formal variation. I hope, his answer seems to…

More
Joined homeone
8 January 2020

Australia's largest home building and renovation
community with over 1.7 million posts

Home
Pros
Forum
Start a new topic
About
Advertise
Contact Homeone
Articles
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2020

Australia's largest home building and
renovation community
Homeone
About

Terms
Privacy

Follow homeone on FacebookFollow homeone on Twitter
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2020