Building Inspector for PCI
I have been using Houspect at progress stages for my new build. (Slab, Brick Plate Height, Roof Cover, Lockup).
They are prompt & efficient - Report usually e-mailed to me within…
Is your new house build behind schedule ? ** Poll **
For my build it was definitely the "office/admin" part of things that has held up the build.
It took 2.5 months for initial plans then another 4 months for final plans…
Is your new house build behind schedule ? ** Poll **
Signed prelim agreement end of Sept 2009 and Sales Rep informed us "about 12 months" build time.
It took 12 months just to get the pad down. Jan 2011 and…
Building with Plunkett Homes Perth
Oddly enough my wife sent an e-mail to Midland Brick last night querying the availability of the brick we selected after Plunkett said it was at least 3 months until…
Building with Plunkett Homes Perth
The Builder's Margin in my contract is also blank, despite me asking for the sum to be included it came back blank.
I have also been advised at this late stage…
Building with Plunkett Homes Perth
Milestone achieved today...!
Pad went down today.
It took some perseverance to get here and sometimes I doubted if I would see it.
Roll on bricks…
Building with Plunkett Homes Perth
Fixed costs for siteworks in WA would be a rarity as there are so many variables. Site surveys, engineers reports, etc and experience give the builder a good idea…
Building with Plunkett Homes Perth
G'day Karratha and thanks for your post.
Strangely enough I wanted to build with ABN Group (Alcock Brown-Neaves) but the reps said that they didn't/couldn't build in my area as it…
Building with Plunkett Homes Perth
Thanks Toby - It's been a while coming!
Cheers,
Wrexy...
Building with Plunkett Homes Perth
Hi AG,
Thanks for your post. If you were thinking about going 3 phase later down the track it can be expensive to upgrade to 3 phase (Upgrade feed in…
Building with Plunkett Homes Perth
My earthworks finally started last week...!
After many months of playing the waiting game, Plunkett also tell me they are ready to get a building licence once my earthworks…
Building with Plunkett Homes Perth
Hi AG,
3 phase power is one of those "nice to have" things that can be done later, but it does cost a lot less to do when building the house…
Building with Plunkett Homes Perth
G'day Alex,
My experience with siteworks in the hills so far is that you need to have deep pockets - or at least factor in the cost of siteworks to the…
Building with Plunkett Homes Perth
Good to read how everyone's builds are coming along - It looks like we are all at a similar stage so watching progress will be interesting...!
Building with Plunkett Homes Perth
Hi Toby,
Not sure if you're in Mandurah or Rockingham Shire, but it may pay to go in and talk to them about going outside the building envelope.
My shire and contract…
Building with Plunkett Homes Perth
Hi Mrslin - I'm hoping there is a building licence in the mail soon too!
I would prefer the timber roof frame over the steel roof frame as I've only ever…
Building with Plunkett Homes Perth
Now onto Final Plans Mk3. Still no sign of a building licence from shire. There are 4 Plunkett builds in my area so I'm sure it will be planned to…
Building with Plunkett Homes Perth
Every retailer from fast food joints, supermarkets, liquor stores, petrol stations and electrical retailers all try to reel the customer in with low prices then tempt you to part with…
Building with Plunkett Homes Perth
Sandhurst in Kalamunda sounds good. It sounds like a popular display for Plunkett.
Having built a few times, the general rule is the basic/bottom end is usually the standard range…
Building with Plunkett Homes Perth
Hi Fulhamfc,
It wasn't too hard - I just asked the question to the pre-start person and it was crossed out there & then for Plunkett not to do the earthworks.
Plunkett…
Building with Plunkett Homes Perth
Hi Toby,
I got my tank through at Malaga. There is scheme water at my block, so the tank isn't needed for the build, but will have lots of roof…
Building with Plunkett Homes Perth
Hi mrslin,
We are building in the hills, where timber and termites will be aplenty!
We have sent back final plans 2 weeks ago, so still playing the waiting game for them…
Building with Plunkett Homes Perth
Hi Mrslin,
No start date from Plunkett yet - I talk to them a couple of times a week at least trying to move things. My docs are with the local…
Building with Plunkett Homes Perth
Hi AG,
From memory the Caufield does have terracotta tiles. Bristile have a small display out at Armadale brickworks plus a few other metro display centres where you can see the…
Building with Plunkett Homes Perth
G'day AG,
I think we were also told by the sales rep that we could select either colourbond or roof tiles (I got the impression that select either meant 'no charge'…
Building with Plunkett Homes Perth
G'day AG,
I think I saw a similar plan on the wall in the Sandhurst display at Baldivis as well as the 5 bedroom version.
I'll be interested to see…
Building with Plunkett Homes Perth
I'm planning to make the Sandhurst lounge room into the home office/study/computer room for yours truly...!
My better half has put dibs…
Building with Plunkett Homes Perth
Hi AubinGrover,
I'm guessing that is the Sandhurst version for standard suburban blocks that has been turned 90 degrees and has the entrance & carport where the ensuite is on the…
Building with Plunkett Homes Perth
Hi AubinGrover,
Also building a Sandhurst with Plunkett. Going for a colour scheme that was used on one of their previous display homes (Toodyay Lodge) including tiles instead of Colourbond.
…
Building with Plunkett Homes Perth
Hi mrslin,
We were about 6-7 weeks from signing prelim agreement to getting draft plans, then another week or so to pre-start. Since then it has been 4 months of to'ing…