Please help builder screwing me up
Hi all,
We singed a NSW fair trading contract early this year the finish date on contract is Mid June still not completed. At the time of signing the contract…
The Ponds - Ridgeline
congrats @Sydney-build the min set back on the side boundaries are 900mm i don't think you can get any concession on the side boundaries. I am not sure about the…
The Ponds - Ridgeline
We are trying to build a retaining wall in our backyard which will serve as a garden bed too. Something like this.
of course without the ugly post in the front.…
The Ponds - Ridgeline
Thanks @mattandkatehome we only have 1m on the side looks like we need to stick that ugly thing in our backyard
The Ponds - Ridgeline
Did any one change their water tank location after starting the build? I wanted it to be moved towards the side. Is that even possible?
The Ponds - Ridgeline
Yes 22.5 is the standard We went for it instead of 25 Deg as we dont have any plans in using the attic space for storage or as an additional…
The Ponds - Ridgeline
It's getting on very slow sure the our private builder is not fast as project builders. I guess I am banking on more flexibility ,time will tell figures crossed.
The Ponds - Ridgeline
congrats @vijat1 i see your roof truss are all been done. BW is really moving fast you will be in no time.
BTW anyone know how long did the banks take…
The Ponds - Ridgeline
With all the non stop rains it proving a bit of challenge to get the slab down. hopefully going to get it done by this Monday.
And also when you go…
The Ponds - Ridgeline
@Vijay1 My opinion is to go to 2.7 the pros weight much more than corns here In grand schema of things 4-6 weeks is well worth a wait to get…
The Ponds - Ridgeline
Congrats on your slap now the rain can help it cure !!!
@dotgif and @mattandkatehome were spot on cannot think of anything to add to it. On the good side…
The Ponds - Ridgeline
Thanks Vijay1
Garage door will be decided later once the brick work is done very hard for me to visualise stuffs...
The Ponds - Ridgeline
Lm for piers various have heard the Owner builders paying as low as 30 ish to 70. BTW i was thinking before quote they must have structural specifications which clearly…
The Ponds - Ridgeline
Any one else using Austral Expression Range Black Stone brick?
Roof: Bristle Classic Coal
Windows : cedar on the front, Black rest
Gutter and down pipes : Black
Fascia :SurfMist
Facade:Partially rendered bricks on top…
The Ponds - Ridgeline
Quick Update so far:
Feb 14: Building contract signed
Feb 20: Bank approved
Feb 24: Excavation
Feb 25: Piers
Feb 26: Inspections
Feb 27---- till now rain
I am not sure if they can…
The Ponds - Ridgeline
I am building with a private builder till now he seems to be a good cooperative guy.
He was a brickie and carpenter by trade. If you want his details…
The Ponds - Ridgeline
My house was on the zone of influence Piers needed to get checked by Sydney Waters.
The Ponds - Ridgeline
@Vijay
Good to know you are on Berambing too.
Congrats on the start of ur build.
I guess it would have been easy to level the backyard while the excavator…
The Ponds - Ridgeline
People building on Bermanbing street How do you have you backyard done. I mean its slopping towards the alfresco do you level it out and have a retaining wall at…
Rangehoods - which type is best?
hi,
Ducted is the one which sucks the air into roof space / out of the roof. Recirculating is the the you find in most apartments.
Ducted rangehood in general…
The Ponds - Ridgeline
@Dotgif thanks, yeah lucky my neighbours are all building single storey homes. We are also building single storey.
The Ponds - Ridgeline
hello all,
Sorry took a long break from this thread.
Finally things are moving on my side..