Hi everyone,
Did anyone had to do a "Dilapidatoin Report" before construction started? If so how do we get that organised?
Rgds
Building with Allworth Homes in NSW
WEEK 17: Supervisor rang me on Tuesday to confirm the handover is ready by next week !!! yuy!!! its done !!!
Only issue is bank work will not be completed by…
Building with Allworth Homes in NSW
Hi
Supervisor supposed call me this week and inform about the handover date.
Regarding your issue, Contact the head office reception and get the construction office number and building managers name…
Building with Allworth Homes in NSW
WEEK 16: Paint job completed 14/10. But still need to clean-up the paint on windows and etc.
Only thing left this week is to do with all the fittings..electrical, taps, shower…
Building with Allworth Homes in NSW
WEEK 15: Bench Top installed. Tilling Completed. Painting stated on 7/Oct, Thursday.
Not sure how long the painting job will go. I m thinking 2 weeks, need to check with the…
Building with Allworth Homes in NSW
WEEK 14: Kitchen completed except for the Bench top. Skirting boards, internal window frames and Doors installed. Grage Door yet to be completed. Preparation work for wet area tiling completed.…
Building with Allworth Homes in NSW
Yea some thing went wrong with formatting. Actually Not sure what to look for. We have no experience in building houses. Couldn't see any obvious issue. So I m thinking…
Building with Allworth Homes in NSW
WEEK 13: All the corners completed. Waterproofing completed on 24/09.
Supervisor said, next is lock-up stage where doors will get installed.
WEEK 12: Internal walls completed on 14/09. They are working on…
Building with Allworth Homes in NSW
WEEK 11: Basic internal Electrical wiring completed. 1/2 of wall insulation completed.
Forgot to check the roof insulation. Sheets for internal wall have arrived as well.
WEEK 10: Bricklaying finished on…
Building with Allworth Homes in NSW
WEEK 9: Frustrating. Nothing much to write; bricklaying still going on. Looks like it will take another 5 days to complete.
One person doing bricklaying with-out any help, I don't think…
Building with Allworth Homes in NSW
WEEK 8: 11 days of Bricklaying, still not completed yet. Front of the house, couple of sides in the garage, two pillars in front and one pillar at back yet…
Building with Allworth Homes in NSW
WEEK 7: Bricks laying have started. We had sunny 5 days as well. Front of the house and garage yet to be completed. Also they have only completed up to…
Building with Allworth Homes in NSW
WEEK 6: 1/8 (MON) completed the roof tiles. Bricks arrived at the site (3/8). But the from Wed~Sun it rained
So only 2 rows of bricks…
Building with Allworth Homes in NSW
Not sure.. have to ask the supervisor next week.
Building with Allworth Homes in NSW
WEEK 5: Gutters installed. Fitting of roof tiles started today 29/07.
Expected to finish by Monday. But gutters on side of the house…
Who is building with Allworth Homes
Does anyone know the cost to put a brick like "earth" from austral or "mild steal" from PGH ?
Who is building with Allworth Homes
Does anyone know the cost to put a brick like "earth" from austral or "mild steal" from PGH ?
Building with Allworth Homes in NSW
WEEK 4: Frame completed 21/07. Windows installed. Next roof
WEEK 3: Slab completed on 13/07.
WEEK 2: Work for Piers Completed 07/07.
WEEK 1: Excavation completed. The temporary…
Building with Allworth Homes in NSW
WEEK 4: I went today and I was surprised see that the Frame work is almost completed. Little bit of work left on the roof. Window frames have arrived at…
Building with Allworth Homes in NSW
WEEK 3: Slab completed on 13/07... Waiting for the Invoice now .
WEEK 2: Work for Piers Completed 07/07.
We had issues with doing the…
Building with Allworth Homes in NSW
WEEK 2: Work for Piers Completed 07/07.
We had issues with doing the piers; they…
Building with Allworth Homes in NSW
WEEK 1: Excavation completed. The temporary fence around the block is in place, temp Toilet in...
Hopefully slab will go soon..
Building with Allworth Homes in NSW
Quick Note....
I went on Sunday to the land and its been leveled. Initial ground work completed.
It was a big surprise...
Finally...some change on…
Building with Allworth Homes in NSW
20th Day have lapsed... Called Allworth homes this week, they said I should get a letter stating the supervisor details. But not letter yet.
I'm not sure what is going on,…
Building with Allworth Homes in NSW
Hi to people reading this...
Contacted the head office to check the start date, since our '20th day' is due next week friday, they told us we will be contacted next…
Building with Allworth Homes in NSW
ALL worth customer service team have send us the final construction documents set to sign yesterday.
Customer service team really helped us around with the documents and other issues. Great work…
Building with Allworth Homes in NSW
No good news....
Now the documents stuck in the drafting dept for 4 days !
And the golden 20 days to start construction doesn't kick-in as yet.
Another week delay.
Building with Allworth Homes in NSW
Guess what... we haven't still started construction yet.
After few weeks wait finally, bank gave construction approval today.
Just to remind first time builders, the unconditional approval is NOT the final…
Building with Allworth Homes in NSW
Finally Documents are through from Allworth Engineering team to Customer Service Team.
The have been really helpful.
We are signing the contract this week.
Then have to wait for finance confirmation before…