building-expert
Suing builder after failed negotiations at CBS?
Free advice is worth what you pay, nothing.
The difference between professional advice and free advice is likely to be success / failure.
Don’t forget you will still have to pay for…
Flat Roof - Pooling Water
Dipped roof is either a structural weakness or damage to timber frame from termite activity. You should invest in a competent inspection.
Builder refusing to negotiate contract
There are no guarantees in life.
Reputation is a record of past performance and no guarantee of a future.
If you choose your builder based on a good reputation you are merely…
Australian Standards - Free Access
We can send billions of dollars to Ukraine but we cannot have Australian standards free of cost.
Builder using 10mm plasterboard instead of 13mm
You should always use cement sheet lining in external applications however if you do use plasterboard then ensure it is wr water resistant.
About 35 years ago I built a fire…
Builder using 10mm plasterboard instead of 13mm
Yes, substitution of specified plaster lining without your consent is breach of contract
Help slab built too high
I was referring to your relationship with the builder.
In your relationship with land surveyor he is at fault if there is an error with levels. I think you should…
Help slab built too high
On further information you provided its clear builder is not at fault but you, through your own contractor(land surveyor) supplying erroneous data to the builder.
Help slab built too high
There is no excuse for the builder not building to design floor levels. It has now left you wondering not only about adequacy of the slab but also about builder's…
No contract until demolition is done on existing dwelling?
I have come across cases where asbestos cement was burried on site, instead od proper disposal, footings left burried, sites flooded and ruined from inadequately decomissioned services or poor surface…
How to remove Sika?
I know that Prepsol will dissolve silicone, try that
Builder refusing to negotiate contract
Governments are corrupted by industry lobbies.
When our corrupt Building Commission was abolished in favour of VBA the first thing they did was to retain most of existing staff, renamed their…
Is this exposed aggregate normal?
A simple procedure may not have prevented the problem but could have put the owner into a better position in relation to the dispute.
1 check and verify contractors qualifications, registration…
Suing builder after failed negotiations at CBS?
Builders obligation is not only to comply with Acts, regulations and standards but also to conform with contractual obligations.
Rusted gutter is not acceptable
Parapet flashing is to short and must…
Would the Water be coming from retaining wall?
The level of soil under your house should be higher than outside. If there is a retaining wall then it must have proper drainage.
Suing builder after failed negotiations at CBS?
Your roof lashings should be accurately cut and fitted, sealed and pop riveted at joints at 40mm centres. Your parapet flashings should be fixed at 500mm centres. Work should be…
Builder refusing to negotiate contract
Great post from Simeon but I would like to add something no one is talking about, power imbalance.
Mostly you will have inexperienced homeowner dealing with educated and experienced builder who…
Building up to Lock up - Owner Builder Permit needed?
I believe you do because you are second builder on the job. If you sell who is going to warrant portion of work you have done? Who is going …
Stormwater capping for demolition
All existing services should be decommissioned and capped prior to demolition or else you risk rubbish in sewer and stormwater pipes, electrical hazard and gas hazard.
No contract until demolition is done on existing dwelling?
The possible trick here is that if the builder is not doing demolition it could be alleged that the demolition is incomplete and has interfered with the classification of site…
What is the pipe in my backyard
Sewer vent, yes you will smell sewer gasses when you sit in your gazebo.
Insurable event claims
Many people have lodged insurance claim for damage to their home from an insurable event only to find the claim either rejected or the insurer offering a settlement well below…
Engineering Drawings for Double Steel Garage?
The supplier does not have proof of "cost" until invoices are paid, ask for a copy of paid invoices
Building inspector recommendations for Melbourne VIC?
Try Nik from Compliance Building Reports
No Occupational Certificate until all landscaping is done
Unfortunately you were badly advised.
If I did your pre contract review I would have flagged potential issue.
Looks like landscaping has to go in asap, all you can do is try…
No Occupational Certificate until all landscaping is done
This should have been no surprise if you had read development approval condition 28.
Why isn't your builder completing all the work, including landscaping?
There would be appeal provisions for the council…
Provisional variations
It does not matter what the content of building contact is because it is Domestic Contract Act 2000 that has the protocol for the administration of PC sums and Provisional…
Provisional variations
Get a good building consultant to review your contract and give you expert opinion
Builder Terminated contract after Variation Requested
If your builder has terminated building contract (rightfully or wrongfully) your contract is at an end. There is no provision for the builder to come back. Financially the builder has…
Help - Insufficient fall for sewerage house connection
Who designed the house?
About
Occupation
Building Expert, Pre Purchase Property Inspection Expert, Expert in Thermal Imaging for Detection of Building Defects, Expert in Building Contract management and Administration, Expert Witness
Interests
Incurable student of almost everything