Procorp - Administrator appointed
Hi all, we're very sorry to hear some of you are still doing it tough. We have sent our 90 day list of things to fix about two weeks ago…
Procorp - Administrator appointed
Hi All, we have been in our house since Nov 8th. Still have no phone line as yet and no internet courtesy of the electrician thinking fibre optic would be…
Procorp - Administrator appointed
We had a meeting with our FOURTH Sekisui supervisor this week. So frustrating as you have to go over every detail again as there is not much communication between supervisors.…
Procorp - Administrator appointed
Hi Dan, yeah, they have removed two posts now. I haven't abused them, but have been quite critical and my friends have all shown their support which is good to…
Procorp - Administrator appointed
I wish I had something to say other than expletives. No major progress this week, just fixing up things that were incorrect. Still waiting for carpet, electrician, splash-back to be…
Procorp - Administrator appointed
We must be in the same boat. We were told three weeks ago we could expect to move in this weekend. There has been about 4 days of work since,…
Procorp - Administrator appointed
We are 5 weeks over contract. We were told last week that we should be finished in three weeks. Ha! Given the progress this week I would say 10 weeks…
Procorp - Administrator appointed
Still plodding away at our house, three weeks over contract. Garage door is on, toilets in, vanities in and paint done. The quality of the work leaves a lot to…
Procorp - Administrator appointed
Hi All, hopefully you are moving along well. Very happy to hear you have moved in brown2. We must have two very different arms of Sekisui working for us. We…
Procorp - Administrator appointed
Hi all, I thought I'd fill you in with my developments. Not too much to report actually. Our contract runs out on 8th August and I would be surprised if…
Procorp - Administrator appointed
We've had a few supplies delivered a couple of days ago and there is someone out there this morning digging a trench, presumably to connect the electricity. We still haven't…
Procorp - Administrator appointed
We've been contacted twice by Sekisui now to let us know that the original cornice and laundry tub we selected are no longer available and that an equivalent will be…
Procorp - Administrator appointed
They delivered the portaloo to keep me happy after I grilled them on why they haven't started work when the 20-working day window to re-commence had come and gone. Apparently…
Procorp - Administrator appointed
Some good news and some bad news today. The portaloo has arrived, so that means they 'have started on-site' and therefore the three month contract period starts now according to…
Procorp - Administrator appointed
I received a call from Brian Thompson, special project manager at Sekisui. He couldn't give me a straight answer on why the 20 day breach has happened other than the…
Procorp - Administrator appointed
So our 20 day window to re-commence is today and nothing has changed. I emailed Sekisui and the response was rubbish. "Purchase orders have been placed, management are currently allocating…
Procorp - Administrator appointed
We agree with Liars 100%. At the current rate of construction and lack of communication, they are making Procorp look good! Our 20 day period is next Monday and…
Procorp - Administrator appointed
Liars - how long was the contract you signed with Sekisui? You sound like you are almost done. We have a 12 week contract and agree that at $1 a…
Procorp - Administrator appointed
I think that was a smart move Brown2.
We have sent our contract back complete with signatures. The last issue was had was the progress payment schedule. They wanted payment after…
Procorp - Administrator appointed
Thanks for the info Herewego. This seems to be going against what SICorp have told us though. If we get any extra bills surely we can send them to…
Procorp - Administrator appointed
Brown2: I wouldn't worry about not getting a copy of the approval. The defects were all listed in our contract with a price next to them that SICorp is covering,…
Procorp - Administrator appointed
We sent our contract back today, but it isn't as complete as we would like it. We've listed some points below that might be helpful.
* We queried the liquidated $1/day…
Procorp - Administrator appointed
Hi Dan, we have our bricks 98% complete (still waiting on a new sized window and bar above the garage door to be bricked in) and a roof and all…
Procorp - Administrator appointed
STOP PRESS! Our contract is in hand!
I haven't had a proper read just yet, but most things seem fine so far. The cost estimate is ~$100k more than we…
Procorp - Administrator appointed
The email said:
"I have spoken with the accounts they have received the approval today from the insurance company. Accounts will prepare the progress payment schedule by the end of the…
Procorp - Administrator appointed
We just received an email. Apparently something has been approved by the insurance company and is now in Sekisui's hands, who will now PREPARE THE CONTRACT which we should have…
Procorp - Administrator appointed
I received a call from a Sekisui customer service lady today who was ringing to explain the situation. She said a new contract has been drawn up and is currently…
Procorp - Administrator appointed
We received a call from Mark from Sekisui today - two weeks after we sent out letter in. I had goosebumps I was so excited! Having a meeting on Thursday…
Procorp - Administrator appointed
We are still waiting anxiously. Phone doesn't leave my pocket! To those who have had meetings, did they say anything about having to re-choose selections? Or has everyone who has…
Procorp - Administrator appointed
We looked up that link and the photo on the cover of the Southernvale homes '2012 Inclusions' brochure is a photo of a Procorp design, the Kiewa Signature, the…