HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
Thank you all for the responses. One of the email he sent me was "UNFORSEEN CIRCUMSTANCES" as the title then sends me a variation for daily cost of the delay.…

HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
The builder has not done any work but site cut. I tried to call him to negotiate . What is the definition of commencement? There is an ambiguity around this…

HIA Contract Clause 16.2 Delays to Carrying Out the Works Af
Hello!
Can someone please advise me this Clause 16.2?
My builder is giving me a large variation due to our site having absestos after site cut, We had to organise…

Removing items from contract
Thank you for your reply. Yes maybe the word overthinking was not the right word. I didn’t mean it like that. Sorry if you thought I was rude or anything.…

Removing items from contract
Thanks for your honesty.
I think you are overthinking this. Every build is different, people change their minds all the time. Hence there are variations. You can’t have it perfect first…

Slab design - contract issues
So just a quick update. The builder has now deleted the piering cost. He said it was base on good will. I have asked multiple times if there was something…

Removing items from contract
Hi Everyone,
So we have signed our contract and have paid 5% deposit. The contract includes a swimming pool and prime cost for cabinetry kitchen and laundry.
I’m not a big…

Slab design - contract issues
The trees we have is all in the back of the land and we have cut it all down.

Slab design - contract issues
Yeah the builder didn’t want to go with my design as it was conventional and he wanted to use the waffle design for economical.

Slab design - contract issues
Also I got a conventional slab design done from my engineered and it only had 10 piers.so I don’t know why the builders engineer required 62 piers.

Slab design - contract issues
Thanks for the reply. We demolish the house , and did the soil test straight away. So it’s a class P Otherwise Class M. The geotech and building designer said…

Slab design - contract issues
Hi All,
Our builder has asked us to pay almost 12k extra for extra piercing for the waffle raft slab as there are 62 piers.
I asked the builder several times…

HIA HOME CONTRACT
Okay so the builder said was pretty flexible and he said he will fix the default interest rate lower (18%) and the late completion as the default $50 per day.…

HIA HOME CONTRACT
Thanks everyone for replying. Luckily I have not signed the contract yet and I only put $500 to get the ball rolling. As I organised the preliminary items like soil…

HIA HOME CONTRACT
Hi,
I’m about to sign a contract with a builder and in the contract for the default interest rate they put 45% and the late completion damages is $5 per day.
If…