Home
Pros
Forum
  • About
  • Register
  • Contact
InboxSent
MembersPros
WatchingStarredHistory
RuffTuff
242 Posts
Bronze Member

Follow
242Posts1LikeMost Active Topics

RuffTuff

Chittering
Joined 26 April 2014
Bronze Member
Followers
3 d3 dRuffTuffRuffTuff posted:
EcoStay building project

We got all the flashing installed last week and that's really tidied the roofing up nicely.
Now for the guttering. We've chosen a 150mm half round gutter. The gutter clips offered…

25 d25 dRuffTuffRuffTuff posted:
EcoStay building project

I reckon you'd have no trouble getting a room done with one days hire of the equipment. A whole house might take two days. Cost is around $500 including the…

26 d26 dRuffTuffRuffTuff posted:
EcoStay building project

I'm no expert in polished concrete. This will be our first floor in polished concrete. We've already done a test sample and we like the look.

We polished this…

EcoStay building project
1 month1 monthRuffTuffRuffTuff posted:
EcoStay building project

All the downstairs walls are now up to the floor of the upper level. Time to catch up on some wiring and plumbing jobs. This work takes time but shows…

2 months2 monthsRuffTuffRuffTuff posted:
EcoStay building project

Progress update. This is the easy part just about done. From here on up we're going to be working on scaffold.

EcoStay building project
2 months2 monthsRuffTuffRuffTuff posted:
EcoStay building project

One of the walls will be curved. This was originally planned to be a straight square corner however the idea of curving it instead stuck with us. Now it's becoming…

EcoStay building project
3 months3 monthsRuffTuffRuffTuff posted:
EcoStay building project

We're building a wall in the downstairs bedroom. This particular wall will be mudbrick and about 3m long. It has no windows or other features.
So, we've decided to put…

4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

The store room walls are just about done. The walls are 350mm thick and offer great protection from the outside environment. We wanted a couple of small windows on the…

EcoStay building project
4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

We have a dam that will (depending on summer rain) almost dry out by summer's end.

Once the water level is low enough we can drive the tractor in and dig…

4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

We've had a change in the weather (it's been cooler and a few showers) so not really mudbrick making weather. There are now over 600 stored under cover.

We've taken…

  ⋅  1
4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

Last year we made enough mudbricks to complete this project, however since then we used a heap to build a kitchen for the studio and we've also made a few…

EcoStay building project
4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

We're going to be needing about 45 square meters of decking boards later. We have this huge Wandoo in our front yard that died four or five years ago.

So we've…

4 months4 monthsRuffTuffRuffTuff posted:
EcoStay building project

We hired a concrete grinder for a day and ground the floors to reveal the glass. We've gone down to 120 grit and now sealed it. Once the walls are…

EcoStay building project
  ⋅  1
5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

While we're watching the concrete set we've made a start on the stairs. It will be a curved staircase and as you've seen, the steps are of solid Jarrah. We'll…

  ⋅  1
5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

It was a big day here. Fifteen cubic meters of concrete went into the floor.

And we added the crushed glass.

Should come up nicely when we grind it back.

5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

While we're waiting for Wednesday's concrete delivery we are preparing the timber for the stairs. We milled it some time ago and it's been drying under cover. These timbers are…

EcoStay building project
5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

We've crushed up hundreds of bottles and now have about 250kg of glass standing by ready to add to the concrete floors.

EcoStay building project
5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

Ready for the concrete trucks. This sand has packed down so hard it's like digging into concrete.
All our levels are looking good and we have a nice cool day forecast…

  ⋅  1
5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

Concrete trucks are ordered for Wednesday...better get the formwork in place!

5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

It was quite an effort getting the 10.5m roof panels up 6m with each weighing 126kg. We had to fashion up a crane from some old trusses.

But it's all…

5 months5 monthsRuffTuffRuffTuff posted:
EcoStay building project

The floor joists are in and we have a temporary floor in place. The building is taking shape.

6 months6 monthsRuffTuffRuffTuff posted:
EcoStay building project

Our roofing panels have arrived....to much excitement here.
At 10.5m long the driver did well to get up the driveway.
We're going to work on the subfloor bearers and joists next so…

EcoStay building project
6 months6 monthsRuffTuffRuffTuff posted:
EcoStay building project

Working on backfilling the space behind our stone retaining walls.

Sure is nice to have some level ground to work on.

EcoStay building project
6 months6 monthsRuffTuffRuffTuff posted:
EcoStay building project

All the poles are up now. The building now looks like a shape that could be a house!
We scored the use of an old truck mounted cherry picker (ex electricity…

7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

With the cellar done and the stone retaining walls all but finished we have been working on putting up poles. Poles for the verandahs and some internal. Those that will…

7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

Just finished the last of the stone retaining walls. This one on the east side has the cellar door in it.

EcoStay building project
7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

20 bags of cement, a couple of ute loads of stone, a load of sand from the bag paddock, two cement mixers and a couple of hours.

We now have a…

EcoStay building project
7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

We are only using the concrete blocks for building the cellar. We wanted something that was cheap, easy and quick and would (when filled with concrete & rebar) hold the…

7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

No, haven't done. The entire structure will be underneath our building and above the natural ground level. The site is also extremely well drained, we don't even get puddles during…

7 months7 monthsRuffTuffRuffTuff posted:
EcoStay building project

I've always wanted a cellar. The back end on the house is 2 meters high and will be back filled with soil before we build a studio on it. Seems…

Most Active Topics

EcoStay building project
71 Posts
More
Joined homeone
26 April 2014

Australia's largest home building and renovation
community with over 1.7 million posts

Home
Pros
Forum
Start a new topic
About
Advertise
Contact Homeone
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2019

Australia's largest home building and
renovation community
Homeone
About

Terms
Privacy

Follow homeone on FacebookFollow homeone on Twitter
All comments made express the views and opinions of the author and not the Administrators, Support nor Homeone Australia & New Zealand
© Homeone Australia & New Zealand All Rights Reserved ‎2001 - 2019