Rawson Seaview 36 - Schofields
So PCI went through well with some minor cosmetic issues identified that needed to be rectified. Somehow Garage door dint work during the PCI so that also needed to be…
Rawson Seaview 36 - Schofields
SO house seems almost ready, on 22nd Dec all the trades and Site Super visor dispersed for new year vacation and expected to be back by 10th Jan 2021 onwards.
Have…
Rawson Seaview 36 - Schofields
Week 26 Update - Visited the site today and got chance to look at the complete flooring work. Timber and Carpeting work completed this week. The work completed yesterday only…
Rawson Seaview 36 - Schofields
Week 25 Update - flyscreen installed to all doors and windows, Painters did their job on the balcony cedar and down pipes, shower screens installed, fire place installation completed, Driveway…
Rawson Seaview 36 - Schofields
Congratulations Mguerre76. Do let me know if you have any query, will try to help you with the best possible knowledge I have with Rawson.
Rawson Seaview 36 - Schofields
Construction Week 1 - Good news, finally the work has started on site and era of pre-construction has come to end. Visited site on 30th May and saw the little…
Rawson Balmoral 38 MK1 - Newcastle NSW
I thought I’d take the time to try and share our experiences as we build our Rawson Balmoral 38 MK1.
We had been looking to buy a pre-existing built house…
Rawson Home Review
Rawson Home Review
Thought to post our experience with Rawson Homes Central West branch.
We started a tender late last year (2019).
So far everything has been smooth sailing between Dubbo…